JD Fields & Company
Outlook draft opened with the SOE and buyout PO(s) attached -- review before sending.
Outlook draft opened with the SOE and buyout PO(s) attached -- review before sending.
Documents are not being saved.
Documents are NOT being saved. Nothing can be written into C:\Users\TBiggs\JD Fields & Co\Wortham Tower - Documents\Biggs\Trunkline Folders ([WinError 2] The system cannot find the file specified: 'C:\\Users\\TBiggs\\JD Fields & Co\\Wortham Tower - Documents\\Biggs\\Trunkline Folders\\.packettracker_write_test'). That folder is inside OneDrive, which is the usual cause: pause syncing, or set the documents folder to a plain local folder under Settings.
Change the documents folder
61-110656Complete
FEDERAL STEEL SUPPLY, LLC
Customer PO PO-104934 · <Salesperson 61 Tom Biggs> · FOB HOUSTON, TX
Est ship
09/01
2 days past
Order value
$6K
1 SOE line
Quoted GP
$1K
22.9% quoted
Buyout cost
$0
across 0 POs
Docs verified
0 of 3
3 still to check
SOE entered
Material secured
PO issued
PO emailed
Released to coater / fab
Shipped to job
Tallied & invoiced
SOE Detail — 61-110656
Rep: Tom Biggs
Bill Complete
✉ Email SOE (Outlook) + New Buyout PO
Order details Ship to WILL CALL · N30 · FOB HOUSTON, TX Edit

SOE Line Items

Release material
1 of 1 lines sourcedHow each line is being sourced is shown in the Buyout column.
Item#LocSize / DescriptionQtyUOMUnit PriceAmountCostGP $BuyoutVerify
SRL-81517-10 HTI48" OD X .375" WALL, DSAW API 5L X52M PSL-2 21.0 FT$262.50 $5512.50 $202.2800
$1264.62 Stock #SRL-81517-10+ buyout
+ Add Line

Add SOE Line

For adding one more line to an existing order. To build a whole new order with stock-number autofill, use New SOE from the nav.

Buyout Purchase Orders

No buyout POs on this packet yet. Use "+ New Buyout PO" above to create one.

Cost Sheet & Invoicing

✓ Fully verified
Every stock line, buyout PO, and costed document on this packet has a confirmed cost and footage. Ready to bill.
💰 Invoice this Bitch
$5,512
Sale Value $
$1,265
Gross Profit $ (suggested)
$0
Buyout Cost $
$5,512
Margin Check
+ New Buyout PO

Uploads

Cost Sheet Documents

Upload Bills of Lading, tallies, invoices, or mill certs for this order. Each one is read for total footage and any order #, PO #, or work order # on it as a cross-check against this packet -- nothing changes automatically.
Upload Document
Drop a BOL, tally, invoice, or mill cert here (PDF or text), or click to browse
TypeFileFootageAmountVerifiedIdentifier FoundUploaded
Customer correspondence 104934 jd fields.pdf 08/24/2026
Could not read it: Anthropic API call failed: Error code: 503 - {'type': 'error', 'error': {'type': 'overloaded_error', 'message': 'API key validation is temporarily unavailable. Please retry.'}, 'request_id': 'req_011CeMrTUiHAiknaxTi57cyx'}
Mill cert / MTR 48x375x52_Seah26.pdf 870 08/26/2026
Read off it: footage 869.5, PO PO25300089(91-1237), work order PE202601-0041-000041(5032406). Total footage summed from 8 line items across 2 pages. One line (no. 8) shows wall thickness of 1.000" instead of the 0.375" shown on other lines and on the order specification.
Cost Sheet Cost Sheet 61-110656.xlsx 09/03/2026

Check Against Customer PO

Optional, any time -- upload the customer's actual PO (PDF or text) and this checks it against what's already saved on this SOE. Nothing is changed automatically; any deviation found shows up below for you to review and fix with one click, or leave alone.