JD Fields & Company
61-110428Complete
Weiler Pipe LLC
Customer PO PO- · <Salesperson 61 Tom Biggs> · FOB Houston, TX
Est ship
Order value
$3K
1 SOE line
Quoted GP
$643
20.7% quoted
Buyout cost
$0
across 0 POs
Docs verified
0 of 2
2 still to check
SOE entered
Material secured
PO issued
PO emailed
Released to coater / fab
Shipped to job
Tallied & invoiced
SOE Detail — 61-110428
Rep: Tom Biggs
Draft
✉ Email SOE (Outlook) + New Buyout PO
Order details Ship to WILL CALL · Net 30 Days · FOB Houston, TX Edit

SOE Line Items

Release material
1 of 1 lines sourcedHow each line is being sourced is shown in the Buyout column.
Item#LocSize / DescriptionQtyUOMUnit PriceAmountCostGP $BuyoutVerify
ST-82628-05 HTI16" OD X .500" WALL, ERW API 5L X52 PSL2 42.0 Feet$74.00 $3108.00 $58.7000
$642.60 Stock #ST-82628-05+ buyout
+ Add Line

Add SOE Line

For adding one more line to an existing order. To build a whole new order with stock-number autofill, use New SOE from the nav.

Buyout Purchase Orders

No buyout POs on this packet yet. Use "+ New Buyout PO" above to create one.

Cost Sheet & Invoicing

✓ Fully verified
Every stock line, buyout PO, and costed document on this packet has a confirmed cost and footage. Ready to bill.
💰 Invoice this Bitch
$3,108
Sale Value $
$643
Gross Profit $ (suggested)
$0
Buyout Cost $
$3,108
Margin Check
+ New Buyout PO

Uploads

Cost Sheet Documents

Upload Bills of Lading, tallies, invoices, or mill certs for this order. Each one is read for total footage and any order #, PO #, or work order # on it as a cross-check against this packet -- nothing changes automatically.
Upload Document
Drop a BOL, tally, invoice, or mill cert here (PDF or text), or click to browse
TypeFileFootageAmountVerifiedIdentifier FoundUploaded
Tally Shipper 61-110428 SH 3496 JDF.pdf 42 61-110428 match 08/31/2026
The document shows multiple pages with slightly different footage values. Page 1 (Houston Tubulars Shipping Report Cover Sheet) shows footage as "42.00" handwritten. Page 3 (Houston Tubulars tally sheet) shows "Total Footage: 42.00" at bottom and "REQUIRED FOOTAGE: 40.00" above it. The tally shows 1 piece with heat# ZP1199. Page 6 (JD Fields release tag) shows "FOOTAGE 40" highlighted in yellow. There's a discrepancy between the stated footage (42.00 actual vs 40.00 required). Using 42.00 as the actual total footage shipped per the tally. The release/work order number appears to be 61-110428 consistently across documents.
Cost Sheet Cost Sheet 61-110428.xlsx 09/03/2026

Check Against Customer PO

Optional, any time -- upload the customer's actual PO (PDF or text) and this checks it against what's already saved on this SOE. Nothing is changed automatically; any deviation found shows up below for you to review and fix with one click, or leave alone.
Upload PO to Check Drop the customer PO here (PDF or text), or click to browse
{} {} {} {}